Found 33 content(s) with At 07:00 pm on July 29th, 2016, the last wind turbine (the 52nd turbine) of the Bac Lieu Wind Farm Phase II has been successfully installed by HTLs engineers and workers. Displaying from 1 to 10.
htl winning bidder for 20 turbine foundations of the bac lieu wind farm phase ii
After 10 wind turbines of the first phase have been operated successfully on the Bac Lieu Sea, the Bac Lieu Wind Farm continues its second phase ...
16 wind turbines e 103 of enercon have been installed successfully
After 6 months installing the first E 103 wind turbine of Enercon at Ninh Thuan site, the last wind turbine of Mui Dinh Wind Farm – Phase 1 was successfully installed on 13th February 2019 by HTL engineers and workers. Such event was marked with their endless effort for working through days and nights, extreme climate conditions to successfully fulfill phase 1 as scheduled...
company news 1
After completing the power connecting infrastructure for 110kV power line, 22kV power line, 22/110kV substation, cable connecting bridges, The Bac Lieu Wind Farm – Phase I has connected to the nation’s grid and officially generated power since early June, 2013....
62 turbines of the bac lieu wind farm phase i ii have been successfully completed
At 07:00 pm on July 29th, 2016, the last wind turbine (the 52nd turbine) of the Bac Lieu Wind Farm - Phase II has been successfully installed by HTL's engineers and workers.
completed the construction and installation of the bac lieu wind farm phase i

In the afternoon of October 02, 2012, one year after completing the first ...

htl constructed transported and installed turbines of the bac lieu wind farm project phase ii
In spite of extreme weather conditions which included high waves, strong winds, worked days and nights, 52 wind turbines with its capacity of 83.2MW has been successfully constructed, transported and installed by HTL's engineers and workers for the Bac Lieu wind farm - phase II- which is the first wind power plant in the Mekong Delta and the first offshore wind energy in Asia.
first photos of the bac lieu wind farm phase ii
Tower sections are transported from Phu My port to Cai Cui port -Can Tho province for checking before acceptance, then transport to the Bac Lieu wind farm jobsite for installation phase II. Tower sections are transported by Nooteboom extendible trailer and Goldhofer hydraulic trailer, 02 trailers are usual in oversize cargos transportation....
project 1

INSTALL WTG FOR THE BAC LIEU WIND FARM

completed transportation installation of the phu lac wind farm phase i
In the afternoon 01:06pm of August 28, 2016, the last 12nd turbine of The Phu Lac wind farm - TBW Phase I of 12 wind turbines with total capacity 24MW has successfully installed, to ensure safety, quality and scheduled progress by HTL's engineers and workers. The power connecting infrastructure for 22/110kV substation will be completed before the National Day of Viet Nam on September 02nd as expected.
the phu lac wind farm in binh thuan province
On June 6th, 2016, Huy Hoang Transportation and Logistic Corp. (HTL) has been successfully installed the first wind turbine of total 12 wind turbines in The Phu Lac wind farm - Phase I be invested by Thuan Binh Wind Power J.S.C (EVN-TBW). The EVN-TBW was founded in 2009 with 75% its capital from The Electricity of Viet Nam (EVN) Group.